1. Power Plant Operations
  2. Process
  3. Respond to operational events
Process · Respond to operational events

Respond to operational events

Follow an outage, alarm, maintenance event or curtailment through recovery.

Step by step

  1. Raise the event Plant Operator

    Plant Operator records site, type, description and the actual start time with Open status.

    • Starts the response record.
    • Updates Operational events, Sites
  2. Acknowledge response Operations Manager

    Operations Manager reviews the Open event and changes it to Acknowledged.

    • Shows the event has an owner for response.
    • Updates Operational events
  3. Assign site work Operations Manager

    Operations Manager records a task, site, assignee and due date where work is needed.

    • Gives the technician a specific assignment.
    • Updates Maintenance tasks, People, Sites
  4. Confirm recovery Operations Manager

    Operations Manager records the end time and marks the event Resolved after checking the intended response.

    • Closes the response with its actual recovery time.
    • Updates Operational events, Maintenance tasks
Plant Operator
, Operations Manager.

Set up Power Plant Operations your way.

Start free, then use Proto to change fields, steps and approvals before your team goes live.