1. Wind Farm Management
  2. Features
  3. Turbine performance
Feature · Turbine performance

Turbine performance

Production intervals with wind speed and availability.

OverviewTurbine production intervals
Wind Farm Management · Turbine performance

Turbine production intervals

Turbine intervals

New
IdTurbineStarts atEnds atEnergy k whWind speed MPS
IDD-354TRB-1270113 Oct17 Oct660760
IDD-808TRB-5469311 Oct15 Oct90550
IDD-972TRB-6877907 Oct10 Oct230250
IDD-425TRB-1950004 Oct07 Oct910820
IDD-151TRB-8239115 Oct18 Oct520650
6 of 6 records
IDD-354Turbine intervals · TI-96894
TurbineTRB-12701
Starts at13 Oct
Ends at17 Oct
Energy k wh660
Wind speed MPS760
Example screen with sample data

What you can do

See what each turbine produced, and why

Turbine production intervals record, for each turbine and period, the energy produced in kilowatt-hours, the wind speed in metres per second and the minutes the turbine was available. Put together, they answer the question owners ask most: when the wind was there, was the turbine there too? A turbine with high wind speed and low energy over the same interval has a problem. A turbine with low wind speed and low energy had a quiet day.

Intervals are recorded by the operations engineer and submitted as evidence to the performance reviewer. The original interval is kept. A correction is added as later evidence linked to the same turbine, not written over the first figure, so the record shows both what was first reported and what was corrected, and when.

How the work is organized

Production is recorded per turbine and per period, and reviewed before it is used in performance reporting.

  • Attributed records. Each interval is recorded by a named person through their linked user account, so a question about a figure goes to the person who entered it.
  • Corrections add, never overwrite. A wrong interval is corrected with new evidence; the original stays.
  • Availability next to energy. Available minutes sit beside energy and wind speed, so lost production can be split into “not available” and “available but not producing”.

What to agree during setup

Agree the interval length you report on, and whether intervals come from the turbine controller system or are entered from shift reports. Agree who reviews production evidence and how quickly. Decide how availability is counted for a curtailed turbine, since it is available but held back. Prepare examples of a normal interval, an interval during a curtailment, an interval with a wind speed sensor fault and a corrected interval.

Check the handoff on an actual case

During a windy afternoon one turbine shows normal wind speed but only half the energy of its neighbours. The operations engineer records the intervals as reported and logs an alarm event on the site. The performance reviewer sees the low energy against the wind speed and the open event in the same period, and holds the intervals for follow-up instead of approving them into the monthly figures.

The technician later finds a pitch fault. Corrected availability is added as later evidence for those intervals, and the review outcome is recorded. The monthly availability report shows the reduced available minutes for that turbine and that day, with the event that explains it.

What your team sees

  • Turbine production intervals — Energy, wind speed and available minutes per turbine and period.
  • Turbine status board — Current operating state for every turbine.

Follow the work through

See the reports built on production intervals.

What it keeps track of

Data model
Turbine intervals
Per-turbine production intervals with wind speed and availability.
Turbines
Individual wind turbines with rated capacity and operating state.

Who uses it

Permissions
Operations Engineer
, Performance Reviewer.
The operations engineer records production; the performance reviewer reviews it.

Set up Wind Farm Management your way.

Start free, then use Proto to change fields, steps and approvals before your team goes live.

How to get started